Summer Construction Update 2019

Wednesday, July 17, 2019 - 3:59pm

Our construction crew has been working hard this summer and our new buildings are taking shape!  We will be providing monthly updates on Construction; please see below for July 2019:

Library/Office:  The contractor has completed framing and sheathing for the two-story building, and is nearing completion on exterior plaster. Clay tile roofing work is also underway, and should be completed by the end of this week.  Mechanical, electrical, plumbing and fire sprinkler rough in work is nearly complete. Interior walls are framed and insulated, with drywall work in progress on the first and second floor walls.  Painting of walls will begin in two weeks, with ceiling grid installation to follow in early August.

 

MP Room: Steel erection is complete. Exterior wall framing for Building 2 is in progress and will continue through July. Concrete stem walls and ramp work has begun on the interior and exterior.  Glu Lam beams for the roof structure will be erected in late July.

 

Sitework: Temporary removal of the AKC play structure is complete, with the grading and fill for the new play structure area beginning this week Forming and pouring of perimeter curbs will take place next week. Re-installation of the play structure should begin in late July, with poured rubber put in place in early August, in time for the start of school.

Addison News