Construction Update: September 5, 2018

Wednesday, September 12, 2018 - 1:14pm

 

The Contractor has completed installation of reinforcing steel and installing batter boards and edge forms for the foundations. They will set column bolt templates  this week and plan to pour the footings soon.

We will send out a confirmation of the pour date when it is finalized. Note that on this date, there will be concrete trucks coming to the site every 20 to 30 minutes, and there will be a pump truck set up on the site to pour the concrete. There will be some increased traffic on Webster that day, but the trucks will enter/exit and stage on the site, with minimal back up alarms. Other construction noise will be moderate during the pour with the increased number of workers needed for the pour.

The schedule for the AKC portables manufacturing is unchanged this week. The portables are scheduled to be delivered on September 22, and they will take the remainder of the following week to assemble the portables and install ramps and skirting around the perimeter.  There will be 6 trucks delivering the portables that day, and they will drop them off using the field gate access off Lincoln Ave. We will have more details on this activity in next week’s update.

Addison News

  • Construction Update: September 19, 2018

    September 19, 2018: The Contractor has been delayed in manufacturing anchor bolt templates, which has stalled foundation work.


  • Principal's Message, 9/17/2018

    Dear Addison Families, thanks to everyone who attended the Principal's Coffee this past Friday; we had approximately 40 parents representing K-5 families so it was great to connect and hear your thoughts. 


  • Construction Update: September 5, 2018

    Construction updates for September 5, 2018: The Contractor has completed installation of reinforcing steel and installing batter boards and edge forms for the foundations. They will set column bolt templates  this week and plan to pour the footings soon.


  • Principal's Message, 9/3/2018

    Dear Addison Families, It was great to see so many new and returning families at Back to School Night this past Tuesday.


  • Construction Update: August 28, 2018

    Aug 28, 2018: The Contractor has completed installation of reinforcing steel in the foundations, and are currently installing batter boards and edge forms. 


  • Construction Update: August 13, 2018

    August 13, 2018: The Contractor has completed digging out foundations for Building 1, and has compacted the bottom of the footings for approval by the soils inspector. 


  • Construction Update: August 13, 2018

    Construction update for the week of August 13, 2018:  The Contractor has completed digging out foundations for Building 1, and has compacted the bottom of the footings for approval by the soils inspector. 


  • Welcome Back to School!

    Welcome back message from Principal Boyce on August 3, 2018


  • Construction Update: July 31, 2018

    July 31, 2018: The Galileo and Wheels camps are now over, and we are happy to report that there were few, if any issues during the summer...


  • Construction Update: July 18, 2018

    July 18, 2018: The Contractor has begun preparing the pad for Building 1...