Construction Update: September 19, 2018

Tuesday, September 25, 2018 - 10:18pm

Below is a quick update on the construction progress at Addison for this week:

  1. The Contractor has been delayed in manufacturing anchor bolt templates, which has stalled foundation work.  They are being built in the shop this week, and will be installed next week.
  2. The foundation concrete pour is tentatively scheduled to occur on one day during the window of October 3-5. Confirmation of the final date will be provided when it is set.
  3. The portables for AKC are scheduled to be delivered on Saturday, September 22nd.   There will be 6 trucks delivering the portables, and they will drop them off using the field gate access off of Lincoln Avenue.  Workers will be on site next week to assemble the portables and install ramps and skirting around the perimeter.
  4. The keystone wall around the AKC portable slope is being installed this week, and should be done by Friday, September 21.