Construction Update: March 6, 2019

Wednesday, March 6, 2019 - 2:04pm

This week’s update on construction progress at Addison.

Building 1:  Sausal has completed wall framing on the first floor, and has moved to framing the 2nd floor deck and 1st floor shear walls. 2nd floor framing and roof framing will commence next week.

Glu Lam beams have been assembled and will be set sometime in the next two weeks. Electrical and plumbing rough in work has commenced on the first floor.

Building 2: Grading for the Building 2 pad is complete. Sausal is holding off on beginning foundations until a favorable weather pattern is forecast to avoid washing out the footing excavations.

Sitework: The City of Palo Alto began the fire water line connection on Webster today, and should be finished by tomorrow, pending weather. Street patchwork will be scheduled later in March.