Construction Update: June 5, 2018

Tuesday, June 5, 2018 - 10:30pm

Here is a quick update on the construction progress, and what to expect the next week around the construction site at Addison:

  1. The construction fence has been erected, and hazmat abatement work has begun.  This work should be complete by early next week. Materials are being removed within local containment, and pose no general hazard to workers or students. Air monitoring personnel are on site full time during this work to ensure air quality is maintained.
  2. Given the progress of the abatement contractor, it looks like demolition of the building will begin as early as the middle of next week. I have requested a demo plan from the contractor to describe how they intend to physically demo the building, and what noise and dust protection measures they’ll employ to mitigate any impact to campers and neighbors.
  3. Tree removal will begin tomorrow, and continue through Thursday. The contractor will begin tomorrow with the large trees along Lincoln where the Kids Club will be located, and then continue on Thursday to the smaller trees on campus that are within the construction area. This will be a two day activity.
  4. The contractor will also begin working on site demolition (asphalt paving) and utility installation for the new Kids Club, which will continue for the next couple of weeks.
  5. The Day Care portables design has been submitted to DSA for approval by the architect.  Once approved by DSA, Williams/Scotsman can begin assembling the portables in their plant. This work is anticipated to take 3 to 4 weeks.

Back to main construction page

 

Addison News

  • Principal's Message, 10/14/2018

    Hello Addison Families, This past week our Kindergarten students began their full-day program. We are excited to have them on campus for a longer time block!


  • Principal's Message, 10/01/2018

    Dear Addison Families, we had an exciting week with the 3rd Grade Bike Rodeo, Book Fair, and Hoedown!


  • Frequently Asked Questions: Addison childcare portables

    September 25: Principal Boyce answers questions regarding the new Addison Kids Club (AKC) portable buildings.


  • Construction Update: September 19, 2018

    September 19, 2018: The Contractor has been delayed in manufacturing anchor bolt templates, which has stalled foundation work.


  • Principal's Message, 9/17/2018

    Dear Addison Families, thanks to everyone who attended the Principal's Coffee this past Friday; we had approximately 40 parents representing K-5 families so it was great to connect and hear your thoughts. 


  • Construction Update: September 5, 2018

    Construction updates for September 5, 2018: The Contractor has completed installation of reinforcing steel and installing batter boards and edge forms for the foundations. They will set column bolt templates  this week and plan to pour the footings soon.


  • Principal's Message, 9/3/2018

    Dear Addison Families, It was great to see so many new and returning families at Back to School Night this past Tuesday.


  • Construction Update: August 28, 2018

    Aug 28, 2018: The Contractor has completed installation of reinforcing steel in the foundations, and are currently installing batter boards and edge forms. 


  • Construction Update: August 13, 2018

    August 13, 2018: The Contractor has completed digging out foundations for Building 1, and has compacted the bottom of the footings for approval by the soils inspector. 


  • Construction Update: August 13, 2018

    Construction update for the week of August 13, 2018:  The Contractor has completed digging out foundations for Building 1, and has compacted the bottom of the footings for approval by the soils inspector.