Construction Update: June 26, 2018

Wednesday, June 27, 2018 - 6:15am

Below is a quick update on the construction progress at Addison:

  1. The MP building has been demolished and all debris and foundations were broken up and removed last week.  The tile mosaic along the north wall was removed in sections, and is being stored in the container by the AKC play structure.  Some tiles were broken during removal, but should be able to be glued back together before reinstallation.
  2. The survey crew was on site yesterday to stake grades and utility runs.
  3. Demolition of AC paving by the AKC pad work started today, and will continue preparing the pads for the Kids’ Club portables along Lincoln for the remainder of this week.
  4. Utility installations for the new building and the Kids’ Club will begin next week. Utility work within the street will be done by the City, which will likely be scheduled for later this summer.

Back to the construction main page

 

Addison News

  • Construction Update: September 19, 2018

    September 19, 2018: The Contractor has been delayed in manufacturing anchor bolt templates, which has stalled foundation work.


  • Principal's Message, 9/17/2018

    Dear Addison Families, thanks to everyone who attended the Principal's Coffee this past Friday; we had approximately 40 parents representing K-5 families so it was great to connect and hear your thoughts. 


  • Construction Update: September 5, 2018

    Construction updates for September 5, 2018: The Contractor has completed installation of reinforcing steel and installing batter boards and edge forms for the foundations. They will set column bolt templates  this week and plan to pour the footings soon.


  • Principal's Message, 9/3/2018

    Dear Addison Families, It was great to see so many new and returning families at Back to School Night this past Tuesday.


  • Construction Update: August 28, 2018

    Aug 28, 2018: The Contractor has completed installation of reinforcing steel in the foundations, and are currently installing batter boards and edge forms. 


  • Construction Update: August 13, 2018

    August 13, 2018: The Contractor has completed digging out foundations for Building 1, and has compacted the bottom of the footings for approval by the soils inspector. 


  • Construction Update: August 13, 2018

    Construction update for the week of August 13, 2018:  The Contractor has completed digging out foundations for Building 1, and has compacted the bottom of the footings for approval by the soils inspector. 


  • Welcome Back to School!

    Welcome back message from Principal Boyce on August 3, 2018


  • Construction Update: July 31, 2018

    July 31, 2018: The Galileo and Wheels camps are now over, and we are happy to report that there were few, if any issues during the summer...


  • Construction Update: July 18, 2018

    July 18, 2018: The Contractor has begun preparing the pad for Building 1...