Below is a quick update on the construction progress at Addison for this week:

  • The Galileo and Wheels camps are now over, and we are happy to report that there were few, if any issues during the summer. We’d like to thank the camp staffs for working with us during the demolition of the MP building.  This will be the last update for the Galileo  and Wheels staff.

 

  • The Contractor has finished preparing the pad for Building 1 (Admin/Library). They have been delayed laying out the footings waiting for clarification on surveying, but will begin excavation of footings for Building 1 next week.

 

  • Work on utility runs to the portables have been installed, and the pad for the day care portables has been completed.

 

  • The portable manufacturer is making improvements to the Day Care portables in their shops in two locations. Portables are scheduled to be delivered with improvements done on August 10th and 20th. After installation, move in will commence and staff will schedule the certification walkthrough, likely in September.
     
  • Once the Day Care portables are certified and occupied, work will begin on Building 2 (MP Building)

 