Construction Update: July 18, 2018

Thursday, July 19, 2018 - 10:33am

Below is a quick update on the construction progress at Addison for this week:

1. The Contractor has begun preparing the pad for Building 1 (Admin/Library). Work will continue through this week on fill and compaction. Next week they will begin excavation of footings for Building 1, with reinforcing steel and UG utility installation.

2. Work on utility runs to the portables continues this week, which includes power, sewer and water line installation. Work will continue through Friday on this work.
 

3. The portable manufacturer is making improvements to the Day Care portables in their shop. Portables are scheduled to be delivered with improvements done on August 10th and 20th. After installation, move in will commence and staff will schedule the certification walkthrough, likely in September.
 

4. Once the Day Care portables are certified and occupied, work will begin on Building 2 (MP Building)

Back to the main construction page

Addison News

  • Principal's Message, 10/14/2018

    Hello Addison Families, This past week our Kindergarten students began their full-day program. We are excited to have them on campus for a longer time block!


  • Principal's Message, 10/01/2018

    Dear Addison Families, we had an exciting week with the 3rd Grade Bike Rodeo, Book Fair, and Hoedown!


  • Frequently Asked Questions: Addison childcare portables

    September 25: Principal Boyce answers questions regarding the new Addison Kids Club (AKC) portable buildings.


  • Construction Update: September 19, 2018

    September 19, 2018: The Contractor has been delayed in manufacturing anchor bolt templates, which has stalled foundation work.


  • Principal's Message, 9/17/2018

    Dear Addison Families, thanks to everyone who attended the Principal's Coffee this past Friday; we had approximately 40 parents representing K-5 families so it was great to connect and hear your thoughts. 


  • Construction Update: September 5, 2018

    Construction updates for September 5, 2018: The Contractor has completed installation of reinforcing steel and installing batter boards and edge forms for the foundations. They will set column bolt templates  this week and plan to pour the footings soon.


  • Principal's Message, 9/3/2018

    Dear Addison Families, It was great to see so many new and returning families at Back to School Night this past Tuesday.


  • Construction Update: August 28, 2018

    Aug 28, 2018: The Contractor has completed installation of reinforcing steel in the foundations, and are currently installing batter boards and edge forms. 


  • Construction Update: August 13, 2018

    August 13, 2018: The Contractor has completed digging out foundations for Building 1, and has compacted the bottom of the footings for approval by the soils inspector. 


  • Construction Update: August 13, 2018

    Construction update for the week of August 13, 2018:  The Contractor has completed digging out foundations for Building 1, and has compacted the bottom of the footings for approval by the soils inspector.