Construction Update: July 18, 2018

Thursday, July 19, 2018 - 10:33am

Below is a quick update on the construction progress at Addison for this week:

1. The Contractor has begun preparing the pad for Building 1 (Admin/Library). Work will continue through this week on fill and compaction. Next week they will begin excavation of footings for Building 1, with reinforcing steel and UG utility installation.

2. Work on utility runs to the portables continues this week, which includes power, sewer and water line installation. Work will continue through Friday on this work.
 

3. The portable manufacturer is making improvements to the Day Care portables in their shop. Portables are scheduled to be delivered with improvements done on August 10th and 20th. After installation, move in will commence and staff will schedule the certification walkthrough, likely in September.
 

4. Once the Day Care portables are certified and occupied, work will begin on Building 2 (MP Building)