February 5, 2019 Construction Update 

Building 1:  Structural steel erection is nearly complete, with some additional pieces still to come. Plumb and welding work will continue through Wednesday.  Sausal Construction has begun wall framing on the first floor, and will continue for the next two weeks. Second floor framing is also underway, with the second floor deck due to start on February 20th.  MEP rough in work will begin in two weeks.

Building 2: Grading for the Building 2 pad is complete. Sausal will hold off on beginning foundations until a favorable weather pattern arrives so the footings do not get washed out.

AKC: The roof coating mock-up is done and ready for review.