Construction Update: February 26, 2019

Tuesday, February 26, 2019 - 2:01pm

Building 1:  Sausal Construction has completed wall framing on the first floor, and has moved on to the second floor wall framing and deck framing. Shear wall framing is also in progress on the first floor.

Glu Lam beams are being assembled on site. Roof framing and setting of Glu Lam beams will occur in two weeks. Electrical and plumbing rough in work has commenced on the first floor. Door frames have been delivered to the site.

 Building 2: Grading for the Building 2 pad is complete. Sausal is holding off on beginning foundations until a favorable weather pattern is forecast, to avoid washing out the footing excavations.

https://addison.pausd.org/construction