Building 1:  Structural steel erection and welding work is complete with the exception of some minor items. Sausal Construction is completing wall framing on the first floor, and will move on to 2nd floor wall framing and the 2nd floor deck this week. Roof framing and setting of Glu Laminated beams is planned for the next two weeks.  A crane will be on site one day to set the Glu Laminiated beams on the roof level as well. Electrical and plumbing wall rough in work will begin next week.

Building 2: Grading for the Building 2 pad is complete. Sausal is holding off on beginning work on the foundations until a favorable weather pattern is forecast, to avoid washing out the footing excavations.