Construction Update: December 18, 2018

Thursday, December 27, 2018 - 9:43pm

This week’s update on construction progress at Addison. The next two weeks are winter break, so activity will be light until after New Year’s.

Building 1:  The wall curbs were poured on Friday, December 14. Structural steel fabrication is in progress, with steel delivery and erection scheduled to begin the week of January 14th.

Building 2: The AKC portables were visited by the State licensing officials today, and we anticipate certification and move in to the new facilities by the end of the week.

Demolition of the old AKC portables is scheduled to begin January 2nd, and should continue through the 4th. Grading and import of fines for the pad will begin the following week, with footing excavation to follow.

A planting plan along Lincoln and and paint colors for the AKC buildings were adopted on Monday, December 17th.  Staff will finalize agreements with the landscaping and painting contractors and will begin work in the next few weeks.

 