Below is a quick update on the construction progress at Addison for the week of August 28, 2018:

1. The Contractor has completed installation of reinforcing steel in the foundations, and are currently installing batter boards and edge forms. They will begin to set column bolt templates later this week, and are targeting a concrete pour of the foundations for late next week.
 

2. The AKC pads are complete and utilities have been run to the area in preparation for delivery of the portables.
 

3. Portables are scheduled to be delivered with improvements done on September 15, which is a Saturday delivery to avoid students on the field. They will take the remainder of the week to assemble the portables and install ramps and skirting around the perimeter.
 