Construction Update: August 13, 2018

Thursday, August 16, 2018 - 2:30pm

Below is a quick update on the construction progress at Addison for this week:

1. The Contractor has completed digging out foundations for Building 1, and has compacted the bottom of the footings for approval by the soils inspector. They plan to begin tomorrow setting up batter boards and edge forms for the foundations, and rebar installation will begin next week. They are working toward a concrete pour of foundations during the first week of September. As this milestone gets closer, we will send out more information on the plan for this one day activity.

2. The AKC pads are complete and utilities have been run to the area, with electrical runs completed last week.

3. The portable manufacturer is making improvements to the Day Care portables in their shop. Portables are scheduled to be delivered with improvements done on September 5, which is two weeks later than our last update. The manufacturer indicated that this is a very busy part of their season, and they had problems meeting the demand this summer. After installation, move in will commence and staff will schedule the certification walkthrough, likely in late September or early October

4. Around campus, other activities have been completed to prepare for the opening of school today. The trash enclosure has been moved to the Lincoln gates, fences have been moved to secure the AKC area and bike racks have been relocated.

 

Addison News

  • Construction Update: September 19, 2018

    September 19, 2018: The Contractor has been delayed in manufacturing anchor bolt templates, which has stalled foundation work.


  • Principal's Message, 9/17/2018

    Dear Addison Families, thanks to everyone who attended the Principal's Coffee this past Friday; we had approximately 40 parents representing K-5 families so it was great to connect and hear your thoughts. 


  • Construction Update: September 5, 2018

    Construction updates for September 5, 2018: The Contractor has completed installation of reinforcing steel and installing batter boards and edge forms for the foundations. They will set column bolt templates  this week and plan to pour the footings soon.


  • Principal's Message, 9/3/2018

    Dear Addison Families, It was great to see so many new and returning families at Back to School Night this past Tuesday.


  • Construction Update: August 28, 2018

    Aug 28, 2018: The Contractor has completed installation of reinforcing steel in the foundations, and are currently installing batter boards and edge forms. 


  • Construction Update: August 13, 2018

    August 13, 2018: The Contractor has completed digging out foundations for Building 1, and has compacted the bottom of the footings for approval by the soils inspector. 


  • Construction Update: August 13, 2018

    Construction update for the week of August 13, 2018:  The Contractor has completed digging out foundations for Building 1, and has compacted the bottom of the footings for approval by the soils inspector. 


  • Welcome Back to School!

    Welcome back message from Principal Boyce on August 3, 2018


  • Construction Update: July 31, 2018

    July 31, 2018: The Galileo and Wheels camps are now over, and we are happy to report that there were few, if any issues during the summer...


  • Construction Update: July 18, 2018

    July 18, 2018: The Contractor has begun preparing the pad for Building 1...