Construction Update 6/11/2019

Thursday, June 6, 2019 - 10:18am

Below is an update on construction progress at Addison for the week of June 11:

 

Building 1:  The contractor is working on final framing and roofing.  Mechanical, electrical, plumbing and fire sprinkler rough in work is nearly complete. Insulation and drywall work has begun on the first floor walls. On the exterior, scaffolding has been erected and building paper installation is in progress. Lath and plaster activities will continue through June and July.

 

Building 2: Steel erection is complete. Framing for concrete stem walls and ramp work has begun, and wall framing will begin next week.

 

Sitework: Work on raising and improving the AKC play area and play structure has commenced, with demolition of the play structure in progress this week. After the site has been raised, the play structure will be rebuilt, in time for the opening of school in August 2019.  Work in the courtyard has been postponed until summer 2020.