Construction Update, 5/7/19

Tuesday, May 7, 2019 - 3:57pm

Building 1  
The contractor has a couple more weeks of framing to complete sheathing, blocking and soffits in Building 1. The plumber, electrician and mechanical subcontractors are roughing in overhead and in-wall utilities through May. Roofing will begin on Monday, May 13.

Building 2
The slab on grade was poured on Monday, May 6.  Steel erection will re-commence next week and continue for another two weeks. Glu-Lam beams will be assembled on site and then set the last week in May.

Sitework
During the summer, sitework will include work on raising the AKC play structure and renovating the courtyard to improve drainage, install pavers and provide landscaping.

https://addison.pausd.org/construction
 