Construction Update, 5/24/19

Friday, May 24, 2019 - 10:05pm

Below is an update on construction progress at Addison for the week of May 24:

 

Building 1:  The contractor is nearing the completion of framing activities in Building 1 and roofing is scheduled to begin the first week of June. The plumber, electrician and mechanical subs are roughing in overhead and in-wall utilities through May, with work nearly complete on the first floor and beginning on the second floor this week. Scaffolding will be erected this week to begin the exterior plaster operations in June.

 

Building 2: Steel erection continues for the rest of this week. Glu-Lam beams have been assembled and are ready for installation. Framing activities will begin next week now that Building 1 is done. Concrete stem walls and ramp work has also begun this week.

 

Sitework: During the summer, sitework will include work on raising the AKC play structure and renovating the courtyard to improve drainage, pavers and landscaping.

 

Tom

 