Construction Update, 4/17/2019

Wednesday, April 17, 2019 - 7:32pm

Below is an update on construction progress at Addison.

 

Building 1:  The contractor has completed framing on the first and floors, and is now working on roof framing and sheathing of the exterior walls. Electrical and plumbing rough in work in the walls is in progress.  Fire sprinkler and HVAC rough in work will commence next week.

 

Building 2: Foundations were poured on Monday, April 15. Structural steel arrived on site on Tiesday, April 16, and erection of columns will begin later this week. Steel erection will continue through next week, before work on underslab utilities begins the following week.

 

https://addison.pausd.org/construction