Construction Update, 04/23/2019

Tuesday, April 23, 2019 - 6:42pm

Building 1:  The contractor has completed wall framing on the first and second floors, and is working on roof framing, sheathing and sheathing of the exterior walls. Electrical and plumbing rough in work in the walls is in progress. Fire sprinkler and HVAC rough in work on the first floor has also started this week.

Building 2: Foundations were poured last week and erection of the structural steel columns is in progress.  Steel erection will continue through next week. Under-slab electrical work is in progress, with slab base rock, sand and reinforcing steel to begin on Monday.  The slab on grade pour is scheduled for Friday, May 3.

Sitework: No work to report.