Construction Overview

Work on Addison will be done in four phases. Click here to download a document showing all four phases.

  • PHASE 1: June 2018 - September 2018
  • PHASE 2: September 2018 - November 2019
  • PHASE 3: December 2019 - July 2020
  • PHASE 4: June 2020 - August 2020

Please note that timelines are subject to change.  Click here for the latest Construction News and Updates.

As of August 2018, we are currently in Phase 1, demolition. A detailed demolition plan is available, covering the pertinent issues, including: fencing; utilities shut-offs; hazmat abatement; demoliiton procedures; waste removal; and lab testing to confirm waste being sent to landfill is non-hazardous. All Cal OSHA guidelines will be followed, including safety procedures for workers. Work will begin after 8:00 am during weekdays.  No demolition is planned for weekends.

Click here to view our site plan (June 4, 2018).

Below are renderings of the completed project. 